Project Number: 228730
Issue Date: August 2017
d.
WOODARD & CURRAN
WWTE SCADA Upgrades
Nashua, NH
Operation and Maintenance Data
1)
2)
3)
Submit one draft copy of completed volumes 15 days prior
to final inspection. Include 2 copies of completed manuals
with major equipment when equipment is shipped. Draft
copies will be reviewed and returned after final inspection,
with Engineer's comments. Revise content of all sets as
required. For final submission. submit 2 copies of final
volumes, with electronic files in .PDF format on CD or USB
flash drive, within 10 days after final inspection.
Submit data in ring binders with durable plastic covers with
8 1/2 by 11 inch text pages. Cover: title "OPERATION
AND MAINTENANCE INSTRUCTIONS", title of Project,
and subject matter of binder when multiple binders are
required.
Subdivide binder contents with permanent page dividers,
logically organized as described below with laminated
plastic tabs and clearly print the contents. Prepare a Table
of Contents for each volume, with material, equipment, or
system description identified, in three parts as follows:
Part 1: Directory, listing names, addresses, and telephone
numbers of Contractor, Subcontractors, and major
equipment Suppliers, and service representative.
Part 2: Operation and maintenance instructions arranged by
system and subdivided by Specification section.
For each system, identify names, addresses, and telephone
numbers of Subcontractors and Suppliers. Identify the
following:
Significant design criteria
List of equipment with As-Builts certified “As-Supplied”
Parts list for each component
Operating instructions
Inspection, maintenance and adjustment instructions for
equipment and systems
° Lubrication and maintenance schedules
. Maintenance instructions for speical finishes, including
recommended cleaning methods and materials, and special
precautions identifying detrimental agents
° Troubleshooting guides
° Schematic diagrams
Part 3: Material Safety Data Sheets