Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 11/15/2017 - P243

Finance Committee - Agenda - 11/15/2017 - P243

By dnadmin on Mon, 11/07/2022 - 10:19
Document Date
Wed, 11/15/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 11/15/2017 - 00:00
Page Number
243
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__111520…

C-1.34

65.2. The Owner may perform additional Work related to the Project or the Owner may
let other contracts containing provisions similar to these. The Contractor will afford the
other Contractors who are parties to such Contracts (or the Owner, if the Owner is
performing the additional Work) reasonable opportunity for the introduction and storage
of materials and equipment and the execution of the Work, and shall properly connect
and coordinate the Work with theirs.

65.3 If the performance of the additional Work by other Contractors or the Owner is
not noted in the Contract Documents prior to the execution of the Contract, written notice
shall thereof be given to the Contractor prior to starting such additional Work. If the
Contractor believes that the performance of such additional Work by the Owner or others
involves it in additional expense or entitles it to an extension of the Contract Time, the
Contractor may make a claim thereof as provided in Sections 17 and 18.