C-1.5
accordance with the Contract Documents, so that the Project or specified part can be
utilized for the purposes for which it is intended.
2.25 “Supplemental General Conditions’ means modifications to these general
conditions required by a Federal agency for participation in the PROJECT and approved
by the agency in writing prior to inclusion in the CONTRACT DOCUMENTS, or such
documents that may be imposed by applicable State laws.
2.26 “Supplier” means any person or organization who supplies materials or equipment
for the Work, including that fabricated to a special design, but who does not perform
labor at the site.
2.27 “Work” means all labor necessary to produce the construction required by the
contract documents, and all materials and equipment incorporated or to be incorporated
in the project.
2.28 “Written Notice” means any notice to any party of the Agreement relative to any
part of this Agreement in writing and considered delivered and the service thereof
completed, when posted by certified or registered mail to the said party at his last given
address, or delivered in person to said party or his authorized representative on the Work.
Additional Instructions and Detail Drawings. The Contractor may be furnished
additional instructions and detail drawings as necessary to carry out the work included in
the contract. The additional drawings and instructions thus supplied to the Contractor
will coordinate with the contract documents and will be so prepared that they can be
reasonably interpreted as part thereof.
Shop or Setting Drawings. Shop or setting drawings shall be in accordance with the
following:
4.1 The Contractor shall furnish 6 copies of the manufacturer's shop drawings,
specific design data as required in the detailed specifications, and technical literature
covering all equipment and fabricated materials which he proposes to furnish under this
contract in sufficient detail to indicate full compliance with the specifications. Shop
drawings shall indicate the method of installing, the exact layout dimensions of the
equipment or materials, including the location, size and details of valves, pipe
connections, etc.
4.2. No equipment or materials shall be shipped until the manufacturer's shop
drawings and specifications or other identifying data, assuring compliance with these
specifications, are approved by the Engineer.
4.3 The Contractor shall check and verify all field measurements and shall be
responsible for the prompt submission of all shop and working drawings so that there
shall be no delay in the work.
4.4 Regardless of corrections made in or approval given to such drawings by the
Engineer, the Contractor will nevertheless be responsible for the accuracy of such