B-6.1
CHANGE ORDER
No.
PROJECT: WWTEFE SCADA Syst Upgrades DATE OF ISSUANCE:
OWNER:
229 Main St., Nashua NH
(Address)
OWNER’s
CONTRACTOR: Project No. IFB1094-100217
CONTRACT FOR: _WWTF SCADA Syst Upgrades | ENGINEER
ENGINEER’s
Project No.
You are directed to make the following changes in the Contract Documents.
Description:
Purpose of Change Order:
Justification:
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price Original Contract Time
(days or date)
Previous Change Orders Net change from previous Change Orders
(days)
Contract Price prior to this Change Order
Contract Time prior to this Change Order
(days or date)
Net Increase (Decrease) of this Change Order Net Increase (decrease) this Change Order
(days)
Contract Price with all approved Change Orders Contract Time with all Change Orders
(days or date)
This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as
authorized by this Change Order.
Stipulated price and time adjustment includes all costs and time associated with the above described
change. Contractor waives all nghts for additional time extension for said change. Contractor and Owner
agree that the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.
RECOMMENDED: APPROVED: APPROVED: APPROVED:
By: By: By: By:
Engineer Owner Contractor NHDES