B-2.1
AGREEMENT
THIS AGREEMENT, made this day of
the City of Nashua, New Hampshire, hereinafter called "OWNER" and
(Name of Owner)
Electrical Installations, Inc _ doing business as-fani+ndtvidual)-erta-partnership.-or(a
corporation) hereinafter called "CONTRACTOR”.
2017 by and between
WITNESSETH: That for and in consideration of the payments and agreements hereinafter
mentioned:
1. The CONTRACTOR will commence and complete the project of
Wastewater Treatment Facility SCADA System Upgrades
(Project)
2. The CONTRACTOR will furnish all of the material, supplies, tools, equipment, labor and
other services necessary for the construction and completion of the PROJECT described
herein.
3.The CONTRACTOR will commence the work required by the CONTRACT
DOCUMENTS within calendar days after the date of the NOTICE
TO PROCEED unless the period for completion is extended otherwise by the
CONTRACT DOCUMENTS. Completion time for the project will be calculated as
calendar days from the date specified in the NOTICE TO PROCEED as follows:
270 calendar days consecutive calendar days for substantial completion.
365 calendar days consecutive calendar days for final completion.
Liquidated damages will be in the amount of $1,000 for each calendar day of delay from the
date established for substantial completion and $1,000 for each calendar day of delay from
the date established for final completion.
4. The CONTRACTOR agrees to perform all of the WORK described in the CONTRACT
DOCUMENTS and comply with the terms therein for the sum of
FIVE HUNDRED NINETY-ONE THOUSAND TWO HUNDRED EIGHTY DOLLARS ($591,280)