Project Number: 228730 WWTEF SCADA Upgrades
Issue Date: AugustSeptember, 2017 Nashua, NH
1.04 COORDINATION AND SEQUENCING
A. Coordination
1. Ensure that facilities and wastewater system flows are maintained and
remain in service at all times unless otherwise approved.
a. Obtain written approval of Owner for shutdowns. Notify Engineer a
minimum of two weeks prior to any required shutdowns.
b. Prepare a Shutdown Plan for each requested shutdown indicating
what existing valves must be operated by Owner personnel during
the shutdown.
C. Coordinate Work with the Owner and provide public notice, as
required.
2. Maintain access to facilities for the Owner throughout the Project.
B. Sequence
1. Sequence Work to minimize shutdowns and reflect sequencing in the
construction schedule.
2. Sequence Work to minimize disruption to normal facility operations and to
maintain strict compliance with applicable federal, state_and local permit
discharge standards. Use _finish-to-start_relationships_as_the primary
dependency between tasks on the project (i.e. new panel must be installed
tested and operational before dismantling existing control panel.)
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
END OF SECTION