DIVISION 01 - GENERAL REQUIREMENTS Page No. through Page No.
011100 Summary of Work 01 11 00-1 01 11 00-2
011105 Overall General Requirements O01 11 05-1 01 11 05-26
Forms Attached
Submittal Transmittal (Form C-00 62 11)
Application for Payment (Form C-00 62 76)
Request for Interpretation/Information (Form C-00 63 15)
Field Order (Form C-00 63 36)
Work Change Directive (Form C-00 63 49)
Change Request (Form C- 00 63 60)
Notice of Substantial Completion (Form C-00 65 15)
Notice of Completion (Form C-00 65 18)
DIVISION 9 — FINISHES
09 5100 Acoustical Ceilings 09 51 00-1 (3) 09 51 00-6 (3)
DIVISION 26 — ELECTRICAL
260500 Common Work Results for Electrical 26 05 00-1 26 05 00-14
260519 Low-Voltage Electrical Power
Conductors and Cables 26 05 19-1 26 05 19-6
2605 26 Grounding and Bonding for Electrical
Systems 26 05 26-1 26 05 26-4
260534 Raceways, Boxes, and Supporting Devices 26 05 34-1 26 05 34-13
262726 Wiring Devices 26 27 26-1 26 27 26-7
270000 Communications 27 00 00-1 27 00 00-9
DIVISION 40— PROCESS INTEGRATION
406101 Instrumentation and Controls
General Requirements 40 61 O1-1 40 61 01-5
4062 70 SCADA Computers and Software 40 62 70-1 40 62 70-5
Attached: Table 40 62 70-1 List of Existing Software Programs
40 63 43 Programmable Logic Controllers 40 63 43-1 40 63 43-6
406700 Control System Equipment Panels and Racks 40 67 00-1 40 67 00-14