228730 WWTE SCADA Upgrades
Issue Date: September 28, 2017 Nashua, NH
The following replacement section(s) are reissued herewith in their entirety, have an Issue
Date of September, 2017, contain(s) reference to “ADDENDUM NO. 3” in the footer, and text
changes identified by for additions and for deletions.
Section 01 11 00 Summary of Work consisting of 2 pages
Section 27 00 00, consisting of 10 pages
The following new section is herewith added, has an Issue Date of September 28, 2017, and
contains reference to “ADDENDUM NO. 3” in the footer.
Section 09 51 00, Acoustical Ceilings, consisting of 6 pages
Drawing replacement pages/sheets are reissued herewith, have a revision date of September
28, 2017 in the revision block and designated as “ADDENDUM NO. 3”.
Drawing No. E-003, THICKENING ROOM DEMOLITION & INSTALLATION PLANS
& GENERAL RISER DIAGRAM
The following new Drawing(s) are herewith added, have an issue date of September 28, 2017
and designated issued with “ADDENDUM NO. 3”.
Drawing No. S-0001, CONCRETE EQUIPMENT PAD DEMOLITION DETAILS
Drawing No. S-0002, CONCRETE EQUIPMENT PAD INSTALLATION DETAILS
Drawing No. E-007, FIBER OPTIC SITE PLAN
Prepared and Issued by
Woodard & Curran (Engineer) on behalf of the City of Nashua, NH
WOODARD & CURRAN ADDENDUM NO. 3-2