CHANGE ORDER # 12
COMPANY _T Buck Construction
|ATTENTION Bruce Kenney
DATE 10/2/17
PROJECT Nashua Headworks |
LOCATION Nashua NH
.
Hi Bruce, this change order is for added FRP fittings on the odor control
duct. The drawings show a point of C.T.E. that would not fit, the scrubber
was too close to the fan set up so when the existing duct was demo’d, it
took out the offset altogether and we had to rebuild it with additional FRP
45's, pricing is as follows.
2) 20” field fabricated 45 degree fitings @$600 ea
16) Additional labor hrs @$75 nr
Subtotal
AELCO 15% MU
Total amount of this change order is $2,760.00
$1,200.00
$1,200.00
$2,400.00
$360.00