84
Line ' Cost Qty’
No Code Description Type - / Rate / Hrs) Workers Ext
007 125 amp MCC | Material $2,547.00 4.00 -| $2,547.00
bucket
008 Wire Splice parts | Material $150.00) 1.00 -) $150.00
009 Subcontractor Subcontractor $0.00 0.00 - $0.00
Breakout
Labor : $4,425.00
Gross Margin Percent @ 15%: $663.75
Material : $3,504.30
Gross Margin Percent @ 15%: $525.65
Total: $9,118.70
Reservation of Rights
This COR does not include any amount for impacts such as interference, disruptions, rescheduling, changes in the
sequence of work, delays and/or associated acceleration. We expressly reserve the right to submit our request for
any of these items.
Signed By:
Dated: 10/10/2017