Document Date
Meeting Description
Document Type
Meeting Date
Page Number
80
Sn 1 aa cra
Cost: Qty; :
Line No | Code Description Type / Rate: /Hrs|. Workers Ext
006 3/4" Conduit Material $65.00 10.00 -} $650.00
3 pole 20
007 Pole vamp Material $190.00 1.00 -| $190.00
breaker
008 | Subcontractor Subcontractor $0.00 0.00 : $0.00
Breakout
Labor ; $815.00
Gross Margin Percent @ 15%: $722.25
Material : $870.80
Gross Margin Percent @ 15%: $130.62
Total: $1,938.87
Reservation of Rights
This COR does not include any amount for impacts such as interference, disruptions, rescheduling, changes in the
sequence of work, delays and/or associated acceleration. We expressly reserve the right to subrnit our request for
any of these items.
Signed By: Dated: 10/10/2017
Page Image