T. Buck Construction, inc. PROPOSAL 32
249 Merrow Rd Auburn, ME 04210
207-783-6223 * FAX 207-783-3870
{Proposal Submitted to: Phone; (802) 431-1422 Date 9/15/2017
Wright-Pierce Fax: (866) 783-7101
Street: Job Name
230 Commerce Way, Suite 302 Nashua Wastewater Treatment Facility Headworks Upgrade
City, State & Zip Gode: Job Location:
Portsmouth, NH 03801 Nashua NH
Engineer: Job Phone:
Andy Morrill
hereby submit spacifications and estimate for:
Provide labor, material and equipment to saw cut and chip concrete for long influent channel and clean headworks.
Pro Cut
3.5 Days $1800.00/day $ 5,479.00
$ 5,479.00
15% O&P $ 821.85
$ 6,300.85
10% GC $ 547.90
SUB TOTAL $ 6,848.75 $ 6,848.75
General Contractor HOURS RATE
Labor week ending 9/1/17 9 $ 45.00 § 405.00
Labor week ending 9/8/17 22 $ 45.00 $ 990.00
Fork lift operator week ending 9/8/17 3 $ 4800 §$ 144.00
Labor week ending 9/15/17 26 $ 45.00 $ 1,170.00
Labor week ending 9/22/17 48 $ 45.00 $ 2,160.00
Labor week ending 9/30/17 2 $ 45.00 § $0.00
fEquipment
12000 pound jull 1 day $ 500.00
Compressor w/hammer 3 days $ 600.00
Consumables $ 293.48
$ 6,352.48
15% O&P $ 952.87
$ 7,305.35 $ 7,305.35
TOTAL $14,154.10
1) T Buck Construction requests and additional 10 days be added to the contract time
fe Propose hereby to fumish material and labor complete in accordance with above specifications. for the sum of:
FOURTEEN THOUSAND ONE HUNDRED & FIFTY FOUR DOLLARS
Ail material is quarenteed to ba as specified. All work to ba completed ina Authorized
workmaniike manner according fo standard practices Any alteration or Signature
deviation from above specifications invelving extra coats wil be executed only Bruce Kenney
upon witten orders, and will become an extra charge over and above the
estimate. All agreements contigent upon strikes, accidents or delays beyond Note: This proposal may be withdrawn
control. Owner to cary fire, iomedo end other naceasary insurance. Our by us if not accepted within — days.
fkers Gre fully covered by Worlman’s Compensation insurance
Acceptance of Proposal: te above prices, specifications and
work a6 spscifiad. Payment wil be made as outlined above