Jim Donchess
Mayor + City oF NASHUA
November 29, 2017
TO: FINANCE COMMITTEE
FROM: MAYOR DONCHESS
SUBJECT: Change Order #3
The contract with George Cairns and Sons was approved by Finance Committee on May 17, and the
Board of Aldermen on May 23, 2017 in the amount of $1,653,175. This contract is for the construction of
the Park and Ride at 25 Crown Street.
Since that time, there have been two change orders to the contract submitted thus far which changed the
amount of the contract to $1,638,060.80.
A new change order, Change order 3, adds a handrail which was required to comply with the American
with Disabilities Act requirements. This is the final change order for this project. This change order adds
$3,589.50 to the contract amount, bringing the total contract to $1,641,650.30.