Mark A. Mirley Electric
10/19/2017
Dan Callahan
Vice President
Monadnock Commercial Building Co.
32 Fitzgerald Drive
Unit 10
Jaffrey, N.H. 63452
Job Name: Nashua Wastewater Treatment Plant, Nashua NH.
Proposal
This proposal is for CRTU1 Power at Nashua Wastewater Treatment Plant, Nashua NH.
e Install power for CRTU1 make up heat
Material Cost: $5,725.00
15% Mark up $859.00
Material Total: $5,584.00
Labor:
Pipe Installation:
1 man @ $80/hr. x 16 hours = $1,280.00
2 men @$160.00 x 16 hours = $2,560.00
Pull/Termiriation:
2 men @$160.00 x 8 hours = $1,280.00
Labor Total: $5,120.00
Total Proposal: $11,704.00
If you have any question please let me know.
Thanks,
Mark Mirley
41 Elm Street, Unit #8, Stoncham, Ma. 02180
Office #: 781-438-0909 Fax #: 781-835-0018
Email: mirieyelectrici@verizon net