CHANGE ORDER
DATE: 8/23/2017
CACICO# 02
TO: Monadnock Building Co.
32 Fitzgerald Dr. Unit 10
Jaffery, NH 03452
ATTN: Dan Callanan
RE: Nashua WWTF - RTU-3 Roof Duct —
We hereby agree to make the change (s) Specified below:
Add duct on the roof for RTU-3 to avoid the existing beam in the ceiling.
Add roof curbs, duct supports and insulation for the roof duct.
Each Qty , Total
Roof curbs and duct supports. ($950.00 mat. & 6Hrs.) $950.00 1 $950.00
Deduct for existing duct layout ($600.00 mat. & 31 Hrs.) ($600.00) 1 ($600.00}
Add for new duct layout ($400.00 mat. & 34Hrs.) $400.00 1 $400.00
1 $0.00
Total Material $750.00
O.H. & Profit 15% $862.50
a
Labor Hours 9 X $105.00 = $945.00
Materials = $862.50
Subs = $7,339.50
TAXPERCENT 0% Taxes = $0.00
Total = $9,147.00
NEW TOTAL CONTRACT PRICE = $0.00
CAC Project Manager DATE: 9/6/2017
This Change Order Adds Q Days To The Contract Time.
ACCEPT: The above prices and specifications of this change order are satisfactory and
are hereby accepted. All work to be performed under the same terms and conditions
as specified in the original contract unless otherwise stipulated here within.
SIGNATURE OF PERSON AUTHORIZED TO ACCEPT:
DATE:
PLEASE SIGN AND RETURN ONE COPY CAC MECHANICAL SERVICES, INC.
ONLY A SIGNED, RETURNED COPY WILL START THE FIELD WORK.
CAC MECHANICAL SERVICES. INC
68F Stiles Rd.
SALEM, NH 03079