ADDITIONAL WORK
LUMP SUM PROPOSAL
October 27, 2017 REVISED Page 1of9
City of Nashua
Central Purchasing
229 Main Street
Nashua, New Hampshire 03060
RE: Nashua Wastewater Treatment Facility HVAC Upgrades
2 Sawmill Road
Nashua, N.H. 03060
Complete work in accordance with plans by Wright Pierce Engineers dated “Issued For
Bid 3/17”, Addenda 1&2, verifications of existing conditions and subsequent
conversations with Wright-Pierce Project Engineer Kristen Lemansey as it relates to
EWO #0501 for RTU #3. Should you have any questions, or need further clarification,
please feel free to contact me at your earliest convenience.
TOTAL LUMP SUM PROPOSAL AMOUNT $ 11,983.12
(Eleven Thousand Nine Hundred Eighty Three Dollars and Twelve Cents)
Respectfully Supmitted
Dan Callahan — Vice President
Monadnock Commercial Building Co.