[= L OVW EXHIBIT B
ASSESSMENT SERVICES
January 5, 2017
Attn: Noelle Osborne
Re: CSO Flow Monitoring & Alarming
Dear Noelle,
Please find below the scope we discussed and fee schedule for your review. As you will see, there is
an installation cost included that was not part of our original pricing in the RFP. This is due to the
fact that, at the time, the meters were already installed. Also, I was unsure on the estimated duration
of this project, so I included a monthly cost for operation, maintenance and rental at a slightly
reduced rate than previously quoted in the RFP. Please let me know if you have any questions or if
you would like to move ahead with this project and I can generate a more formal proposal.
FEE SCHEDULE
Item Description of Tasks Estimated Unit Total
# Quantity Cost Cost
1 Installation of Equipment 11 Installs $850.00 | $9,350.00
Item Description of Tasks Total Quantity | Unit Cost | Total Monthly
# Cost
2 Operation, Maintenance & Rental 11 Sites $425.00 $4,675.00
(As Described in RFP0298-072015)
After your review of this information please don’t hesitate to call with any questions.
Best regards,
Flow Assessment Services, LLC
+ f Go
Paul P. Casey
Managing Partner