WOODARD & CURRAN
ATTACHMENT A
WOODARD _ pesponsiBILITY OF THE CLIENT
&CURRAN
Provide access to the SCADA System, Computers and other control equipment and
documentation;
Ensure all electrical systems, communications and power are properly functioning to allow the
improvements;
Assumes any existing instrumentation required to implement upgrades including but not limited
to flow, level and chlorine analyzers are properly functioning;
Determine internally with plant personnel the criteria for users, permissions and passwords;
Attend meetings and provide feedback as needed
RESPONSIBILITY OF WOODARD & CURRAN
All tasks in the following TRM list;
Create Wireless Access points at (13) thirteen control panels
Complete Phase 1 — Detailed Design and Bidding Phase: Under this phase, the detailed design
for the plant sites would be completed. Woodard & Curran recommends that the detailed design
for all plant sites (regardless of schedule) be completed as one project for greater efficiency.
The deliverables would be structured so the City can choose the sites to upgrade and develop
a set of contract documents for those sites. This budget assumes one bidding phase.
Complete all work on or before June 30, 2016 contingent upon receipt of purchase order from
the City of Nashua by March 30, 2016.
City of Nashua, NH (#P228730.13) 2 February 16, 2016