Finance Committee - Agenda - 2/3/2016 - P8

By dnadmin on Mon, 11/07/2022 - 09:56
Document Date
Wed, 02/03/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/03/2016 - 00:00
Page Number
8
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__020320…

Te:

From:

Re:

A. Motion:

Discussion:

City of Nashua, Public Works Division

Board of Public Works Meeting Date: January 21, 2016
Jeff Lafleur, Superintendent
Solid Waste Department

Change Order #2 to contract with Northeast Earth Mechanics, Inc.

To approve Change Order #2 to the contract with Northeast Earth Mechanics, Inc.
(NEM) in the amount of $164,340 to continue construction of the residential
setback barrier wall in the Phase II landfill. Funding for this Change Order is
through Department: 168 Solid Waste; Fund: Solid Waste; Account
Classification: 81 Capital Improvements; Activity: Soil Wall.

NHDES Solid Waste Rules prohibit placement of municipal solid waste within
500 feet of a residential structure. The Four Hills lined expansion landfill (Phase
I & II) was designed and constructed with the footprint of the landfill encroaching
the 500-foot setback limit to residences on Farmwood Drive and Pioneer Drive.
In order to comply with the residential setback rule, a barrier must be constructed
within the footprint of the landfill to prevent waste from being placed in the
setback. The barrier wall must be expanded annually as waste elevations in the
landfill increase.

In May 2014 the City solicited bids for construction of Phase 1 of the soil wall
under IFB0593-050514. Six contractors submitted bids for the project with
Northeast Earth Mechanics (NEM) being the lowest bidder:

Vendor Bid results
Northeast Earth Mechanics $163,727.50
Morello Construction $167,337.50
Daniel T. Ladd Site Work $203,300.00
Project Resource Group LLC $234,054.00
Greene & Russell, Inc. $266,000.00
SCS Field Services $297,405.00

Under the original contract in the amount of $163,727.50 Northeast Earth
Mechanics (NEM) began initial construction in July 2014 of the residential
setback barrier wall in the Phase II/Stage I landfill. Per the NHDES approved
scope of work and contract executed June 10, 2014, NEM established a
compacted soil foundation over the primary liner drainage sand and placed four
lifts of concrete waste blocks on the foundation.

Change Order #1 in the amount of $163,912 provided for the continued
construction of the wall to an elevation of 260 feet in the Phase II/Stage 1 landfill.