Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 4/6/2022 - P131

Finance Committee - Agenda - 4/6/2022 - P131

By dnadmin on Sun, 11/06/2022 - 21:44
Document Date
Fri, 04/01/2022 - 08:56
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 04/06/2022 - 00:00
Page Number
131
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__040620…

To:

From:

Re:

I. Motion:

Discussion:

City of Nashua, Public Works Division

Board of Public Works Meeting Date: March 24, 2022

Daniel Hudson, P.E., City Engineer
Engineering Department

2022 Sewer Replacement Project

To approve the award the construction contract for the 2022 Sewer Replacement Project
to SUR Construction West, Inc. of Winchester, NH in the amount of $2,135,950,
contingent upon bond approval. Funding will be through: Department: 169 Wastewater;
Fund: Bond; Activity: Sewer Rehab.

The annual sewer program addresses failing, aged sewers and associated structures and
piping. The 2022 Sewer Replacement Project will replace approximately 4,000 linear feet
of sewer mains along with associated drainage structures and pipes. The contract includes
work on Blanchard St, Clement St, Donna St, Fairview Ave, Kendrick St, Kern Dr, Pike
St, Sunshine Ct and 12" St, along with miscellaneous other locations throughout the City,
Construction is expected to start in May.

Four bids were received on February 10" as follows:

Jennings Excavation, Inc. of Hollis, NH $2,076,630.25
SUR Construction West of Winchester, NH $2,135,950.00
Defelice Corporation of Dracut, MA $2,687,820.50
N Granese & Sons, Inc. of Salem, MA $3,262,920.00

Jennings Excavation, the low bidder, is a well-established local contractor; however,
upon review of their bid concerns were noted with pricing on certain items. A meeting
was held with Jennings on February 22" to discuss the City’s concerns, and upon further
consideration Jennings requested to withdraw their bid on February 23". The City
approved withdrawal of their bid and release of their bid bond without prejudice.

The second lowest bid received was from SUR Construction West, who performed well
on recent sewer replacement projects for the City and we recommend proceeding with
award to them, contingent on approval of associated sewer bonding authority.