Division 9 — Construction Specifications
Legacy Playground at Labine Park
As Amended per Addendum # 2 issued March 24, 2016
ITEM ‘L’ — IRRIGATION DESIGN AND INSTALLATION
A. SCOPE
The contractor will design an efficient, cost efficient and sustainable irrigation system and
install the piping, wires, zone valves, fittings, clamps and sprinkler heads. Design must be
approved in writing by ENGINEER before installation can begin. The contractor will supply all
labor for this work. The contractors scope of work will start at the flood shack located in the
Labine Park Parking lot. The water service is in the south east corner of the building.
B. MATERIALS AND CONSTRUCTION
The parts for the above work will be provided by the city. The city will be responsible for
making the connection in the building, the backflow, and the installation of the clock.
C. MEASUREMENT AND PAYMENT
Payment will be by lump sum. 75 percent of the total will be paid upon completion of the
installation of the equipment, and 25 percent upon on acceptance of its performance by the
City.