Division 9 — Construction Specifications
Legacy Playground at Labine Park
As Amended per Addendum # 2 issued March 24, 2016
ITEM ‘F’ - ENGINEERED WOOD CHIPS
A. SCOPE
This work shall consist of installation of engineered wood chips at the location(s) shown on the
layout plan per the detail of the plan set provided or as ordered by the Engineer.
B. MATERIALS AND CONSTRUCTION
The Contractor shall supply all labor, materials, equipment and transportation necessary for the
required work. The material shall be placed at a minimum depth of 12”.
C. MEASUREMENT AND PAYMENT
Engineered Wood Chips will be measured by the number of cubic yards installed. Payment for
work under these items shall be at the contract unit price per unit and shall include full
compensation for excavation, grading, material, labor, tools, equipment, disposal of
construction debris (existing sidewalk, concrete, asphalt, etc.), and any other incidentals
necessary for the satisfactory completion of this work as specified.