Division 9 — Construction Specifications
Legacy Playground at Labine Park
As Amended per Addendum # 2 issued March 24, 2016
3.03
3.04
Surface Preparation: Using a brush or short nap roller, aoply primer to the substrate
perimeter and any adjacent vertical barriers (such as playground equipment) at the rate
of 300 ft2/gal.
INSTALLATION
Do not proceed with playground surfacing installation until all applicable site work,
including substrate preparation, fencing, playground equipment installation and other
relevant work, has been completed.
Base Layer Installation:
1. Using screeds and hand trowels, install the base layer at a consistent density of
29 pounds, 1 ounce per cubic foot to the specified thickness.
2. Allow base layer to cure for sufficient time so that indentations are not left in the
base layer from applicator foot traffic or equipment.
3. Do not allow foot traffic or use of the base layer surface until it is sufficiently
cured.
Primer Application: Using a brush or short nap roller, apply primer to the base layer
perimeter and any adjacent vertical barriers that will contact the surfacing system at the
rate of 300 ft2/gal.
Top Layer Installation:
1. Using a hand trowel, install top layer at a consistent density of 58 pounds, 9
ounces per cubic foot to a nominal thickness of 0.5".
2. Allow top layer to cure for a minimum of 48 hours.
3. At the end of the minimum curing period, verify that the surface is sufficiently
dry and firm to allow foot traffic and use without damage to the surface.
4. Do not allow foot traffic or use of the surface until it is sufficiently cured.
PROTECTION
Protect the installed surface from damage resulting from subsequent construction
activity on the site.
C. MEASUREMENT AND PAYMENT
Protective Surfacing will be measured by the number of square feet installed. Payment for
work under these items shall be at the contract unit price per unit and shall include full
compensation for excavation, grading, base materials, materials, labor, tools, equipment,
material testing, disposal of construction debris (existing sidewalk, concrete, asphalt, etc.), and
any other incidentals necessary for the satisfactory completion of this work as specified.
Cost to remove and replace failed subgrade material will be paid by the Contractor.