Division 9 — Construction Specifications
Legacy Playground at Labine Park
As Amended per Addendum # 2 issued March 24, 2016
All Items that are not included in the special provision shall comply with the latest approved
NHDOT Standard Specifications for Road and Bridge Construction, the latest approved City of
Nashua Standard Specifications for Road Construction Sewer and Drains, the latest approved
NHDOT Standard Plans for Construction and the latest approved edition of Manual of Uniform
Traffic Control Devices. The most stringent specification shall apply.
Unless otherwise noted all work will be paid for by the quantity actually installed.
Additional Technical Specifications
ITEM ‘670.95’ — TEMPORARY SAFETY FENCE
A. SCOPE
This work shall consist of installation of a temporary safety fence around the project site or as
ordered by the Engineer.
B. MATERIALS AND CONSTRUCTION
The Contractor shall supply all labor, materials, equipment and transportation necessary for the
required work. The fencing shall consist of a temporary 6’ tall chain link fence as per the detail
of the plan set provided.
C. MEASUREMENT AND PAYMENT
Temporary Safety Fence will be measured by the number of linear feet installed. Payment for
work under these items shall be at the contract unit price per unit and shall include full
compensation for excavation, grading, labor, tools, equipment, disposal of construction debris
(existing sidewalk, concrete, asphalt, etc.), and any other incidentals necessary for the
satisfactory completion of this work as specified.