Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/3/2016 - P102

Finance Committee - Agenda - 5/3/2016 - P102

By dnadmin on Mon, 11/07/2022 - 09:54
Document Date
Tue, 05/03/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Tue, 05/03/2016 - 00:00
Page Number
102
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__050320…

or entities identified in the Supplementary Conditions to be listed as insured or additional insured (and the officers,
directors, partners, employees, agents, and other consultants and subcontractors of each and any of them) under such
policies for losses and damages so caused.

ARTICLE 6 - CONTRACTOR’S RESPONSIBILITIES

6.01 Supervision and Superintendence

A. CONTRACTOR shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention
thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the
Contract Documents. CONTRACTOR shall be solely responsible for the means, methods, techniques, sequences, and
procedures of construction, but CONTRACTOR shall not be responsible for the negligence of OWNER or ENGINEER
in the design or specification of a specific means, method, technique, sequence, or procedure of construction which is
shown or indicated in and expressly required by the Contract Documents. CONTRACTOR shall be responsible to see
that the completed Work complies accurately with the Contract Documents.

B. At all times during the progress of the Work, CONTRACTOR shall assign a competent resident superintendent
thereto who shall not be replaced without written notice to OWNER and ENGINEER except under extraordinary
circumstances. The superintendent will be CONTRACTOR’s representative at the Site and shall have authority to act
on behalf of CONTRACTOR. All communications given to or received from the superintendent shall be binding on
CONTRACTOR.

6.02 Labor; Working Hours

A. CONTRACTOR shall provide competent, suitably qualified personnel to survey, lay out, and construct the Work as
required by the Contract Documents. CONTRACTOR shall at all times maintain good discipline and order at the Site.

B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent
thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during
regular working hours, and CONTRACTOR will not permit overtime work or the performance of Work on Saturday,
Sunday, or any legal holiday without OWNER’s written consent (which will not be unreasonably withheld) given after
prior written notice to ENGINEER.

C. The following list of streets may not be opened or worked in between the hours of 7:00 AM and 9:00 AM and 3:00
PM and 6:00 PM, Monday through Friday of each week:

Broad Street

East Hollis Street
Concord Street
Amherst Street

D. W. Highway
Kinsley Street

East Dunstable Road
Main Street

6.03 Services, Materials, and Equipment

A. Unless otherwise specified in the General Requirements, CONTRACTOR _ shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools,
appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and
incidentals necessary for the performance, testing, start-up, and completion of the Work.

B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good
quality and new, except as otherwise provided in the Contract Documents. All warranties and guarantees specifically
called for by the Specifications shall expressly run to the benefit of OWNER. If required by ENGINEER,
CONTRACTOR shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and