B. The policies of insurance so required by this paragraph 5.04 to be purchased and maintained shall:
1. Include as additional insured (Subject to any customary exclusion in respect of professional liability) OVWWNER,
ENGINEER.
2. The CONTRACTOR must maintain the following lines of coverage and policy limits for the duration of the
contract. Any subcontractors used by the CONTRACTOR are subject to the same coverage and limits and is a
subcontractor of the CONTRACTOR and not the OWNER. It is the responsibility of the CONTRACTOR to update
Certificates of Insurance during the term of the contract. Provide coverage for not less than the following amounts
or greater:
General Liability
$1,000,000 per Occurrence
$2,000,000 Aggregate
City of Nashua Additional Insured
Motor Vehicle Liability *coverage must include all owned, non-owned and hired vehicles.
$1,000,000 Combined Single Limit
Automobile Liability
City of Nashua Additional Insured
Workers’ Compensation Coverage according to Statute of the State of New Hampshire:
$100,000 / $500,000 / $100,000
All bidders and subcontractors at every tier under the bidder will fully comply with NH RSA Chapter 281-A,
“Workers’ Compensation’.
It is the responsibility of the contractor to submit to the City of Nashua certificates of insurance for all subcontractors
prior to the start of the project. It is the responsibility of the contractor to provide the City with updated certificates of
insurance for the contractor and all subcontractors 10 days prior to the expiration of coverage. The City may, at
any time, order the contractor to stop work, suspend the contract or terminate the contract for non-compliance. All
subcontractors are subject to the same insurance requirements as the contractor.
3. Include completed operations insurance;
4. Include contractual liability insurance covering CONTRACTOR’s indemnity obligations under paragraphs 6.07,
6.11, and 6.20;
5. Contain a provision or endorsement that the coverage afforded will not be canceled, materially changed or
renewal refused until at least thirty days prior written notice has been given to OWNER and CONTRACTOR and to
each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has
been issued (and the certificates of insurance furnished by the CONTRACTOR pursuant to paragraph 5.03 will so
provide);
6. Remain in effect until final payment and at all times thereafter when CONTRACTOR may be correcting,
removing or replacing defective Work in accordance with paragraph 13.07; and
7. With respect to completed operations insurance, and any insurance coverage written on a claims-made basis,
remain in effect for at least two years after final payment (and CONTRACTOR shall furnish OWNER and each
other additional insured identified in the Supplementary Conditions, to whom a certificate of insurance has been
issued, evidence satisfactory to OWNER and any such additional insured of continuation of such insurance at final
payment and one year thereafter).
C. CONTRACTOR agrees to maintain all required insurance coverage throughout the entire term of the contract. If
CONTRACTOR does not maintain coverage throughout the entire term of the contract, CONTRACTOR agrees that
OWNER may, at any time the coverage is not maintained by CONTRACTOR, order the CONTRACTOR to stop work,
GC - 17 of 53