I CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities or
discrepancies that CONTRACTOR has discovered in the Contract Documents, and the written resolution thereof by
ENGINEER is acceptable to CONTRACTOR.
J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for performance and furnishing of the Work.
ARTICLE 8 - CONTRACT DOCUMENTS
8.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement;
2. General Conditions;
3. Supplementary Conditions;
4. Bid Bond:
5. Bid Form;
6. Performance Bond;
7. Payment Bond;
8. Certificate of Insurance
9. Technical Specifications as listed in Table of Contents
10. Addenda (numbers to ___, inclusive);
11. Exhibits, as listed in the Table of Contents, to this Agreement
12. The following which may be delivered or issued on or after the Effective Date of the Agreement
and are not attached hereto:
a. Written Amendments
b. Change Order(s)
14. New Hampshire Department of Transportation “Standard Specifications for Road and Bridge
Construction”, latest edition, incorporated by reference or unless otherwise indicated.
15 “Manual of Uniform Traffic Control Devices”, latest edition, incorporated by reference.
16 City of Nashua, Standard Specifications for Sewers and Drains, Revised, Approved and Adopted
June 15, 1992, incorporated by reference.
AG -40f6