CITY OF NASHUA, NEW HAMPSHIRE
Legacy Playground at Labine Park
IFB 0651-033116
ADDENDUM NO. 2 - March 24, 2016
Please also note the following items that were discussed at the pre-bid meeting conducted on
March 16, 2016. These items shall be taken into consideration in the preparation of the bid, and
shall be considered to be included in the Contract:
Nick Caggiano discussed the following:
The history of this 4 year project.
Explanation of the role of the Chamber Leadership group.
The history of the location selection.
Neighborhood make up.
Importance of schedule due to the location of the schools.
Description of the Flood Shack and the water service available the contractor is responsible to
bring the irrigation to the building.
City will make connection to the water service in the building and the installation of the
backflow and clock.
The aspect of the community build regarding the playground equipment required by the grant
this will be scheduled by City.
The City will purchase the playground equipment.
Todd Welch discussed the following:
Questions about subbase material requirements for the poured in-place surface: The
manufacturer’s requirements for subbase material were unclear. Clarification is provided below
under Construction Specifications.
Critical dates for bidding. Key dates were read aloud. Dates are:
o Addendum Date: Thursday, March 24, 2016.
o Bid Due Date: Thursday, March 31, 2016
o Notice to Proceed Date: Wednesday, June 1, 2016
© Substantial Completion Date: August 26, 2016
© Final Completion Date: September 12, 2016
Substantial completion was defined as all work being completed except minor punch list items.
1 ADDENDUM 2