ENGINEERING DESIGN PHASE CONTRACT
For Professional Services for Treatment Works
Ill.
IV.
Time Of Completion
A. The ENGINEER agrees that he will submit to
the DIVISION for approval after modification or
revision as recommended by the DIVISION and agreed
to by the ENGINEER, the completed final plans,
specifications, contract, and associated documents in
compliance with the current issue of the DIVISION's
standards of design within 335 consecutive calendar
days following the execution of this AGREEMENT,
and deliver same to the OWNER within 30 calendar
days following the date of final approval by the DIVI-
SION.
B. It is agreed by the parties te this contract that
failure by the ENGINEER to complete the work within
the time stipulated under TJ, A, above may be con-
sidered sufficient basis for the debarment of the ENGI-
NEER from the DIVISION'S Roster of Prequalified
Engineers as provided for under New Hampshire Code
of Administrative Rules Env-Wq 603.08, or the
Assessment of liquidated damages as provided for
under RSA 485-A:; 4, XII.
Compensation to be Paid the ENGINEER
A. Method of Payments Amounts of Fees
|. | Payment to the ENGINEER, for services
rendered, shall be according to the following
schedule:
Monthly billing based on hours and rates
by labor category with mark-up and inci-
dental expenses in accordance with the
attached fee schedule.
2. The OWNER agrees to pay and the ENGI-
NEER agrees to accept for all services under this
AGREEMENT, a fee not to exceed:
Field Study
Complete
Dollars
(Complete)
Preliminary Design (Design Basis)
Four Hundred and Seyenty-Nine Thousand,
and Fifty-One Dollars
($479,051)
Final Design, Bid Documents and _ Bid
Support
2016.05.27 Pump Stations Upgrade Prelim Design Contract
Page 3 of 7
To Be Determined
Dollars
($ TBD).
3. If separate documents are required for
additional construction contracts on this PRO-
JECT, an additional fee as approved by the
DIVISION shall be paid to the ENGINEER.
4. Prior to formal approval of contract docu-
ments by the DIVISION, the ENGINEER shall
make such revisions in them as recommended by
the DIVISION and agreed to by the ENGINEER
without additional compensation. After formal
approval, if it becomes necessary to revise the
contract documents for reasons beyond the
control of the ENGINEER, payment for such
revision or revisions shall be made to the ENGI-
NEER subject to approval by the DIVISION.
Limits of All Payments
1. The ENGINEER hereby assures the
OWNER and agrees that the following fee for
his services (exclusive of surveys, borings, and
certain special services which follow) in con-
nection with the preparation of final plans,
specifications, and contract documents and other
work as generally described under I{A) is
adequate te complete the assignment and shall
not exceed
To Be Determined
Dollars
($ TBD).
2. It is also agreed that payment to the
ENGINEER for services in relation to engi-
neering surveys, including layout and logging of
borings, probings or seismic surveys, together
with plats and project related special services
shall be at actual cost. Actual cost shall include
compensation to the ENGINEER for his work
performed on these services. The ENGINEER
further agrees that the work proposed tinder this
item is enough to satisfactorily complete the
contract documents and that the moneys to be
paid under this item are adequate for the work
proposed and shall not exceed
To Be Determined
Dollars
($___TBD).
02/08/06