Exhibit B
Scope of Services, Contract Time, Fee Schedule
= Integration with other Citywide programs including Pavement Management, MS4
Compliance, etc.
The Plan will identify what is to be performed and the responsible party for
implementation. The plan will also include any secondary responsibilities that may be
required for proper management.
Task F - Implementation Schedule with Cost Estimates
Engineer will develop an implementation schedule for the Plan developed in Task E. The
Plan will also present a schedule that is both workable for the OWNER and compliant with
the permit. Estimated costs will be developed for each item. Costs will include both
operation and maintenance costs, and capital expenditures.
Task G ~ Preliminary and Final Report
ENGINEER will prepare a Preliminary Report of the work performed in Tasks A through F.
The report will include concise recommendations and actions to move forward with
development and implementation of the full plan as required in the Permit. ENGINEER
will provide 5 hardcopies and an electronic copy of the draft plan to OWNER for review
and will meet with OWNER to discuss the plan and any revisions. ENGINEER will prepare
a Final Report based on the review and comments on the draft report. Ten (10) hardcopies
and an electronic copy of the Final Report will be submitted to OWNER. ,
ENGINEER will assist OWNER in making a presentation to the Board of Aldermen to
present the findings and recommendations of the plan.
2. Contract Time Schedule
The time periods for the performance of ENGINEER's Services are as follows:
The period of service for the professional services described above shall commence upon
execution of this Contract and terminate after the final report deliverable. The final report is
expected to be prepared within one hundred eighty (180) consecutive calendar days
following execution of the Contract. Services and costs provided under this Contract for
professional services are based on execution by June 2016.
3. Fee Schedule, Compensation and Invoicing
Compensation for Services of ENGINEER described in this exhibit will be on the following
basis:
a. For Basic Services as detailed in the scope above, at the salary cost of such services for
employees plus 110 percent of the salary cost for overhead and profit plus actual out-of-
pocket expense costs. Salary cost is defined as the cost of salaries (including sick leave,
vacation, and holiday pay applicable thereto) for time directly chargeable to the project;
CDM age 80
Smith resewers