Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 6/15/2016 - P41

Finance Committee - Agenda - 6/15/2016 - P41

By dnadmin on Mon, 11/07/2022 - 09:52
Document Date
Wed, 06/15/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/15/2016 - 00:00
Page Number
41
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__061520…

Neither party shall be considered in default of the performance of its obligations hereunder to the
extent that performance of such obligations is prevented or delayed by any cause, existing or
future, which is beyond. the reasonable control of such party. Delays arising from the actions or
inactions of one or more of Professional Engineer's principals, officers, employees, agents,
subcontractors, consultants, vendors, or suppliers are expressly recognized to be within
Professional Engineer's control.

9. . DISPUTE RESOLUTION. Any dispute not within the scope of section 7 or section 8 shall
be resolved under this paragraph. Either party shall provide to the other party, in writing and with
full documentation to verify and substantiate its decision, its stated position concerning the dispute.
No dispute shall be considered submitted and no dispute shall be valid under this provision unless
and until the submitting party has delivered the written statement of its position and full
documentation to the other party. The parties shall then attempt to resolve the dispute through
good faith efforts and negotiation between the City Representative and a Professional Engineer
representative. At all times, Professional Engineer shall carry on the work under this contract and
maintain and complete work in accordance with the requirements of the contract or determination
or direction of the City. If the dispute is not resolved within 30 days, either party may request that
the dispute be submitted to the Board of Public Works for final resolution. The decision of the
Board of Public Works shall be final and binding on the parties. If either party is dissatisfied with
the decision of the Board of Public Works, that party may immediately terminate the contract under
this paragraph, with Professional Engineer being entitled to compensation for work actually and
satisfactorily performed up to the time of the termination and the City being entitled to all contract
materials in accordance with paragraph 21, and compensation for any additional damages or
expenses incurred in completing the work under the contract, including, without limitation, the
costs of securing the services of other Professional Engineers.

10. NO DAMAGES FOR DELAY. Apart from a written extension of time, no payment,
compensation, or adjustment of any kind shall be made to Professional Engineer for damages
because of hindrances or delays in the progress of the work from any cause, and Professional
Engineer agrees to accept in full satisfaction of such hindrances and delays any extension of time
that the City may provide.

11. INSURANCE. Professional Engineer shall carry and maintain in effect during the
performance of services under this contract:

> General Liability insurance in the amount of $1,000,000 per occurrence; $2,000,000
aggregate;
> $1,000,000 Combined Single Limit Automobile Liability;
*Coverage must include all owned. non-owned and hired vehicles.
> $1,000,000 Profession Liability;
> and Workers' Compensation Coverage in compliance with the State of New Hampshire
statutes, $100,000/$500,000/$100,000.

Professional Engineer shall maintain in effect at all times during the performance under this
contract all specified insurance coverage with insurers. None of the requirements as to types and
limits to be maintained by Professional Engineer are intended to and shall not in any manner limit
or qualify the liabilities and obligations assumed by Professional Engineer under this
contract. The City of Nashua shall not maintain any insurance on behalf of Professional Engineer.

GC 7 of 13