STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
This agreement is made:
BETWEEN the OWNER: City of Nashua, New Hampshire
229 Main Street
Nashua, NH 03060-2019
And the CONTRACTOR: Ted Barry Company, Inc.
and its successors, transferees and assignees
(together “CONTRACTOR”)
For the following Project: Sewer and Drain Pipe and Structure Inspection
(IFB0844-060916)
ARTICLE 1 - THE CONTRACT DOCUMENTS
The CONTRACTOR shall complete the work described in the Contract Documents for this
project. The documents consist of:
1,
NAARWN
8.
This Agreement signed by the OWNER and CONTRACTOR, including the General
Terms and Conditions;
Scope of Work — IFB0844-060916 and addendums issued;
Drawings and Specifications provided in the bid documents;
Ted Barry Co, Inc.- Bid Proposal and Schedule of Values, dtd June 8, 2016;
Change Order Form;
Insurance Certificate;
Written change orders for minor. changes in the Work issued after execution of: this
Agreement; and
Fully Executed OWNER Purchase Order
The Contract represents the entire and integrated agreement between the parties and supersedes
prior negotiations, proposals, representations or agreements, either written or oral. Any other
documents which are not listed in this Article are not part of the Contract.
In the event of a conflict between the terms of the Proposals and the terms of this Agreement, a
written change order and/or fully executed OWNER Purchase Order, the terms of this Agreement,
the written change order or the fully executed OWNER Purchase Order shall control over the
terms of the Proposals
Page 1 of 12