ARTICLE 16—- DISPUTE RESOLUTION
The parties shall attempt to resolve any dispute related to this contract as follows. Either party
shall provide to the other party, in writing and with full documentation to verify and substantiate
its decision, its stated position concerning the dispute. No dispute shall be considered submitted
and no dispute shall be valid under this provision unless and until the submitting party has
delivered the written statement of its position and full documentation to the other party. The
parties shall then attempt to resolve the dispute through good faith efforts and negotiation between
the OWNER Representative and the CONTRACTOR Representative. At all times,
CONTRACTOR shall carry on the work under this contract and maintain and complete work in
accordance with the requirements of the contract or determination or direction of the OWNER. If
the parties are unable to resolve their dispute as described above within 30 days, the parties may
request that the dispute be submitted to the Board of Public Works for resolution. If the parties are
dissatisfied with the decision of the Board of Public Works, the parties’ reserve the right to pursue
any available legal and/or equitable remedies for any breaches of this contract except as that right
may be limited by the terms of this contract.
ARTICLE 17- CHOICE OF LAW AND VENUE
This contract shall be governed exclusively by the laws of the State of New Hampshire and any
claim or action brought relating to this contract, the work performed or contracted to be performed
thereunder, or referable in anyway thereto shall be brought in Hillsborough County (New
Hampshire) Superior Court Southern Judicial District or in the New Hampshire 9th Circuit
Court—Nashua and not elsewhere
ARTICLE 18- MISCELLANEOUS PROVISIONS
1. Neither party to the Contract shall assign the Contract as a whole without written consent
of the other.
2, Tests, inspections and approvals of portions of the Work required by the Contract
Documents or by laws, ordinances, rules, regulations or orders of public authorities having
Jurisdiction shall be made at an appropriate time.
3. If additional testing is required, the CONTRACTOR shall perform these tests.
4, The OWNER shall pay for tests except for testing Work found to be defective for which
the CONTRACTOR shall pay.
Page 11 of 12