  2. Finance Committee - Agenda - 7/6/2016 - P59

Finance Committee - Agenda - 7/6/2016 - P59

By dnadmin on Mon, 11/07/2022 - 09:51
Document Date
Wed, 07/06/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 07/06/2016 - 00:00
Page Number
59
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__070620…

sufficient advance notice that will prevent conflict with their other responsibilities. The City also
agrees to provide Lighting Contractor with access to City records in a reasonable time and
manner and to schedule items that require action by the Board of Public Works and Finance
Committee in a timely manner, The City and Lighting Contractor also agree to attend all
meetings called by the City or Lighting Contractor to discuss the work under the Contract, and
that Lighting Contractor may elect to conduct and record such meetings and shall later distribute
prepared minutes of the meeting to the City.

7. . JMSCOVERY OF CONFLICTS, ERRORS, OMISSIONS, AMBIGUITIES, OR DISCREPANCIES.
Lighting Contractor warrants that it has examined all contract documents, has brought all
conflicts, errors, discrepancies, and ambiguities to the attention of the City in writing, and has
concluded that the City's resolution of each matter is satisfactory to Lighting Contractor. All
future questions Lighting Contractor may have concerning interpretation or clarification of this
contract shall be submitted in writing to the City within 10 calendar days of their arising. The
writing shall state clearly and in full detail the basis for Lighting Contractor's question or
position. The City representative shall render a decision within 15 calendar days. The City's
decision on the matter is final. Any work affected by a conflict, error, omission, or discrepancy
which has been performed by Lighting Contractor prior to having received the City's resolution
shall be at Lighting Contractor's risk and expense. At all times, Lighting Contractor shall carry
on the work under this contract and maintain and complete work in accordance with the
requifements of the contract or determination of the City. Lighting Contractor is responsible for
requesting clarification or interpretation and is solely liable for any cost or expense arising from
its failure to do so. oe

8. TERMINATION OF CONTRACT

A. TERMINATION, ABANDONMENT, OR SUSPENSION AT WILL. The City, in its sole
discretion, shall have the right to terminate, abandon, or suspend all or part of the project and
contract at will, If the City chooses to terminate, abandon, or suspend all or part of the project, it
shall provide Lighting Contractor 10 day’s written notice of its intent todo so. —

If all or part of the project is suspended for more than 90 days, the suspension shall be treated as
a termination at will of all or part of the project and contract.

Upon receipt of notice of termination, abandonment, or suspension at will, Lighting Contractor
shall:

1. Immediately discontinue work on the date and to the extent specified in the notice.

2. Provide the City with a list of all unperformed services.

3. Place no further orders or subcontracts for materials, services, or facilities, other
than as may be necessary or required for completion of such portion of work under
the contract that is not terminated.

4,._ Immediately—make-every reasonable. effort—to—ebtain- cancellation - upon—terms
satisfactory to the City of all orders or subcontracts to the extent they relate to the
performance of work terminated, abandoned, or suspended under the notice, assign
to the City any orders or subcontracts specified in the notice, and revoke
agreements specified in the notice.

5. Not resume work after the effective date of a notice of suspension until receipt of a
written notice from the City to resume performance.

GC 5 of 13