EXHIBIT B
Scope of Work
A. Prepare Preliminary Design Report for Air Handling Units Upgrade
1,
3.
Preliminary workshop. ENGINEER shall attend a preliminary workshop with OWNER to
review the work plan for the air handling units upgrade project, and solicit input on a wide range
of issues including high efficiency air handling technologies, HVAC control alternatives, and
ancillary improvements. Brainstorm on options, and identify the preferred alternatives for
detailed evaluation.
Develop base plans. Engineer shall develop base plans for construction documents using
existing drawing information supplemented by detailed field measurements. This will include
confirming the dimensions of the existing air handling units and ductwork to address conflicts on
several of the existing drawings.
Prepare Preliminary Plans/Report
a. ENGINEER will review existing documentation, observe existing conditions and establish
mechanical system performance requirements. Ventilation, heating and air conditioning
requirements throughout the building will be developed, taking into account details pertaining
to the building envelope, especially roof insulation. The suitability of reusing existing HVAC
equipment based on building envelope improvements, equipment condition and compatibility
with proposed HVAC designs will be evaluated further.
b. Prepare Preliminary Design documents consisting of final design criteria, preliminary
drawings and outline specifications for the selected HVAC equipment (air handling units and
compressors), as well as other recommended improvements. Provide summary of all
building design and support system improvements.
c. Advise OWNER if additional reports, data or other information or services are necessary and
assist OWNER in obtaining such reports, data or other information and services.
d. Based on the information contained in the Preliminary Design documents, submit to OWNER
a Preliminary Construction Cost Estimate.
e. Furnish a draft of the Preliminary Design document and review with OWNER.
f. Receive OWNER comments and provide written response to all comments to satisfaction of
OWNER. Submit final Preliminary Design documents to OWNER for review.
g. The final Preliminary Design Report shall be submitted to the OWNER within 30 days of the
OWNER’s approval to proceed.