Stanley
Jevator Company, inc,
12. Install GFI type outlets in the elevator machine room and pit. Pit outlet should be mounted at least
24” off the pit floor and properly piped to avoid potential water damage.
13. Provide a telephone line to the elevator machine room for communication to the elevator cab
enclosures.
Alarm:
4. Furnish and install smoke detector units in each lobby and in the elevator machine room as
required by ANSI A17.1 2007 code.
2. Furnish and install a signal control module that automatically activates the machine room power
vent in case of fire alarm condition if a mechanical vent system is installed.
3. Furnish and install Four (4) pair of signal feeds from the smoke detector panel or zone modules to
the elevator machine room to facilitate fire service recall function.
HVAC:
1. The elevator machine room temperature must be maintained between 50 and 90 degrees F with
maximum 80% relative humidity, non-condensing. A passive and / or powered means of climate
control may be used for this purpose. Estimated BTU output for elevator equipment will be
provided for your use.
2. Provide hoistway and machine room ventilation to allow removal of smoke and hot gases.
Hoistway may be vented directly to outside air or indirectly, through the machine room slab. The
area of hoistway and machine room vents shall be not less than 3 4% of the area of the hoistway
nor less than 3 sq. ft., whichever is greater. Venting may be either passive or mechanical. If a
mechanical system is installed, a normally closed ampere actuated by a signal from the alarm
panel will be required.
General Builders Work:
1. Provide machine room access door of pre-hung design, steel construction with 1.5 hour fire
rating. Door must be self-closing, self-locking “store room” operation.
2. Provide 2-hour fire rated machine room. Patch voids or cover existing walls, ceiling and exposed
wood as necessary to establish the required rating.
3. Identify, remove and dispose of any hazardous material in the machine room and hoistway prior
to commencement of our work.
4. lf equipment requires the use of a crane to hoist material into or from the machine room,
rooffmachine room hatches or doors sized adequately to allow proper access are to be furnished
and installed by others.
5. Waterproof new pit as necessary.
6. Install pit access ladder.
Page 11 of 13
Proposal # 6021
Ref Id: Mod-09686 - 6/22/2016