CHANGE ORDER
No. 6
PROJECT: 2020 Sewer Replacement Project
OWNER’S CONTRACT NO: IFB0779-021220
EXECUTED CONTRACT DATE: 03/17/20
DATE OF ISSUANCE: 04/13/22 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 155720
CONTRACTOR: SUR Construction West, Inc.
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description:
To mobilize to the intersection of Main Street and Park Street to make emergency repairs to (2) two
sewer mains (see attached map). Because of the complexity of the work, depth (approximately 11”),
location, and proximity to other utilities (gas, communications, water, electric, drain, sewer). The work
will be completed mostly at night and is estimated to take 6 days, weather dependent. Time is of the
essence as barriers are scheduled for installation on Main Street on May 1.
Justification:
The work has been identified to be emergency sewer main repairs.
Attachment:
e Map of location for sewer main repairs, intersection of Main Street and Park Street
e S.U.R Construction West estimate dated April 14, 2022
2020 Sewer Replacement Project 1 of 2 Change Order #6