To:
From:
Re:
E. Motion:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: August 25, 2016
Stephen Dookran, P.E., City Engineer
Engineering Department
Change Order #17 Parkway South — Continental Paving
To approve Change Order #17 of the construction contract with Continental Paving,
Inc. for the Broad Street Parkway South in the amount of $22,627.50. Funding will be
through Department 160 Admin/Engineering; Fund: Bond; Activity: Broad Street
Parkway.
During Construction of the Parkway in the areas of the River Bridge and Millyard
several locations have been identified where additional chain link fence is
recommended to address possible fall hazards.
This Change Order will add to the quantity of chain linked fence in the contract so fence
can be installed at these locations.
The original contract value was $7,102,394 with the approval of this Change Order the
new contract value will be $7,245,608.20.