CHANGE ORDER
No.1
PROJECT: Main Street Sidewalk Improvements — Block 3 & 4
EXECUTED CONTRACT DATE: August 11, 2016
DATE OF ISSUANCE: August 31, 2016 EFFECTIVE DATE: Upon City Approval
OWNER: Citv of Nashua, NH
OWNER’s Purchase Order NO.: 127741
CONTRACTOR: Granite State Curbing Setters, Inc.
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description/ Justification;
An additional 345 LF of 6” Straight Vertical Granite Curbing, for a new walkway from Main Street to Spring
Street Parking Lot, per attached proposal dated August 30, 2016
Change Order # 1 Lof2
TFB0851-052716
Main Street Sidewalk Improvements — Block 3 & 4