Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$1,058,975.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: _October 29, 2016
Ready for final payment: November 18, 2016
Net changes from previous Change Orders
$0.00
Net change from previous Change Orders
None.
Contract Price prior to this Change Order
$1,058,975.00
Contract Times prior to this Change Order
Substantial completion: October 29, 2016
Ready for final payment: November 18, 2016
Net Increase (deerease} of this Change Order
$419,325.00
Net Increase (deerease} of this Change Order
45 calendar days
Contract Price with all approved Change Orders
$1,478,300.00
Contract Times with all approved Change Orders
Substantial completion: December 13, 2016
Ready for final payment: December 23, 2016
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Engineering Name Mayor Jim Donchess
Engineer Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order # 1 2 of 2
2016 Sewer Replacement Program