Summary
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
$149,978.70 Substantial completion:
Ready for final payment:
Net changes from previous Change Orders Net change from previous Change Orders
$0.00
Contract Price prior to this Change Order Contract Times prior to this Change Order
$149,978.70 Substantial completion:
Ready for final payment:
Net Increase (decreasejof this Change Order Net Increase (deerease} of this Change Order
$2,250
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
$152,228.70 Substantial completion:
Ready for final payment:
RECOMMENDED: ACCEPTED: APPROVED:
By: By By
Sarah Marchant Port Lighting Systems Mayor Jim Donchess
(Authorized Signature) (Authorized Signature) Owner
(Authorized Signature)
Date: Date:
Date:
Change Order # 2 2 of 2
Southwest Trails