Finance Committee - Agenda - 11/2/2016 - P107

By dnadmin on Mon, 11/07/2022 - 09:48
Document Date
Wed, 11/02/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 11/02/2016 - 00:00
Page Number
107
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__110220…

ohiBeaulieu, inc. eo!

a Home
544 GAFFNEY STREET » NASHUA, NEW HAMPSHIRE 03060 Builders b
HBRAN (603) 883-5822 FAX# 680.3106 Remocders
MEMBER www. chickbeaulicu.com

City of Nashua Gctober 14, 2016

219 Main St.
Nashua, NH 03060

Project: Nashua Police Department
0 Panther Dr.
Nashua, WH 03062

EPDM ROOF PROPOSAL (REVISED WITH ABSESTOS ABATEMENT)

1. General scope:

Install a new .060" fully adhered RFI EPDM roof system to the lower flat
reofing section (Fleet/Range) as described below. Note, Ail State Abatement
Professionals, INC will be performing the asbestos abatement to include the
following:
* Preparation and isolation of work area
e Installation of engineering controls and decontamination system
® Asbestes abatement of asbestos roofing materials
»* Decontamination of all surfaces
» Encapsulation of all surfaces with lock-down encapsulation
Final air clearance test
« The Nashua Police Department must provide ali electrical and water
requirements for debris removal
« ASAP will make all necessary notifications to ali local, state and
federal regulations

* Upon completion of the asbestos removal, ASAP all documentation
will be submitted to the City of Nashua for the assurance against

and legal entanglements or litigations

2. Tear off:

Remove all stenes from over the rubber membrane and dispose of.
Remove the existing rubber membrane, drip edging and drains fram the
existing roof. The large roof units and the 2 AC units will need to lifted
by J. Lawrence Hall so the existing rubber can be removed and ail new
materials be installed to these locations.

* Remove the existing wood fencing and all 14 supports for the wood posts
around the large roof units.

® Remove the two layers of 1 %” insulation board down to the concrete
decking.

® Remove one roof unit entirely and install new metal decking over the
opening of the unit that will be removed completely off of the roof.