Fooglanlie Cost Estimate
= [iE EF
CITY OF NASHUA
BRIDGE REPAIR CONTRACT
ESTIMATED WORK HOURS
Project | QA/QC | Project Tech. | Total
Manager Sr. Eng. |EngineerEngineey Tech. | Typist! Hours
Prepare Construction Details 4 16 32 24 76
Prepare Quantities and Estimate 1 4 8 13
Prepare Contract Documents 1 4 16 4 25
Bidding Assistance
Advertise Project 1 2 3
Contract Document Preparation and Sales 1 3 4
Contractor Inquiries & Addenda 1 2 2 1 6
Bid Opening Meeting 2 2
Review Bids, Quantities & Contractor - I 1 3 2 7
Prepare Contracts, NOA, NIP, Insurance & 2 2 6 10
Bond Review
Construction Inspection/Administration (8 site visits) 1 8 32 4]
Project Administration & Coordination with City
(Assume | meeting) 2 2 4 : 2
Hour Subtotal:} 11 12 56 74 24 19 196
Project Manager
QC/QA & Senior Engineer
Project Engineer
Engineer
Technician
Technical Typist
P16-0186
ESTIMATED ENGINEERING COSTS
Work Estimated Estimated
Hours Hourly Rate Costs
11 $39.50 $ 435
12 46.51 558
56 39.50 2,212
74 34.48 2,552
24 25.15 604
19 21.34 405
196 Total Direct Labor $ 6,766
Indirect Costs @ 1.434 9,702
Subtotal $16,468
Fixed Fee $ 1,647
Subtotal $18,115
Direct Costs $ 1,015
——_—_—_—_—_—_
TOTAL ESTIMATED COST: $19,130