Construction Inspection and Administration: CLD will provide consultation regarding
design intent or clarification of the plans and specifications. Shop drawings for this
project are not anticipated. CLD will conduct periodic field inspection to ensure work
conforms to the Contract Documents. Field visits will be based on the work being
completed.
Per the Contract Documents (to be developed for the project), CLD (herein known as the
Engineer) will make visits to the site at intervals appropriate to the various stages of
construction as the Engineer deems necessary in order to observe the progress that has
been made and the quality of the various aspects of Contractor's executed work.
Observations and site visits will be limited to the total time amounts discussed above and
in the Fee Estimate unless a further amendment is agreed to. Based on information
obtained during such visits and observations, the Engineer, for the benefit of
Municipality, will determine, in general, if the Work is proceeding in accordance with the
Contract Documents. Engineer will not be required to make exhaustive or continuous
observations on the site to check the quality or quantity of the Work. Engineer's efforts
will be directed toward providing for the Municipality a greater degree of confidence that
the completed Work wiil conform generally to the Contract Documents. On the basis of
such visits and observations, Engineer will keep Municipality informed of the progress of
the Work and will endeavor to guard Municipality against defective work.
Engineer's visits and observations are subject to all the limitations on Engineer's authority
and responsibility set forth in Article 7 of the Contract Documents, and particularly, but
without limitation, during or as a result of Engineer's visits or observations of
Contractor's Work. Engineer will not supervise, direct, control, or have authority over or
be responsible for Contractor's means, methods, techniques, sequences, procedures of
construction, or the safety precautions and programs incident thereto, or for any failure of
Contractor to comply with Laws and Regulations applicable to the performance of the
Work.
We look forward to working with you and City of Nashua on this project. Please contact us if
you have questions or require additional information.
Very truly yours,
Jaime French, P.E.
Project Manager
JF jt
Enclosures
NEW HAMPSHIRE VERMONT MAINE
540 Commercial Streat © Manchester.NH03101 % nh: (603) 668-8723 = fe: {6021 GAR-RAN? © wwwerlidansineers cam