NHDHR inventory forms will include full architectural and site descriptions, a history of the
property, and a contextual analysis to assist NHDHR in its review of the property's role within
the development and/or architecture of the area. The form will also include: a discussion of the
integrity of the property and whether it meets National Register eligibility criteria; images of
historic maps and historic photographs, if located; existing condition photographic
documentation of the property keyed to a photograph location map; and up to three figures
depicting the property layout and relationship to the surrounding area.
This task includes one round of edits from NHDHR (up to 8 hours). VHB will produce one hard
copy on archival paper of each form for submittal to NHDHR.
Task 10. Section 106 Consultation
This task includes coordination and consultation regarding the potential project impacts with
Army Corps of Engineers (ACOE) and/or New Hampshire Division of Historical Resources. This
consultation includes attending meetings and/or the production of a memorandum.
If any of the properties are determined eligible, then VHB will assist in developing the Section
106 Determination of Effects and a Memorandum of Agreement (MOA) if the effect is
determined to be adverse. This task would involve additional consultation with the ACOE,
NHDHR, and the City of Nashua. As needed, VHB would:
e Assist in completing a Determination of Effects table and memorandum;
e Complete the ACHP adverse effects report for submission via e106. An initial draft of the
report will be provided to the City and the Corps for review. One round of review is
anticipated. The final package will be provided to the Corps for electronic submission to
the ACHP, with copies to the City:
e Assist in identifying mitigation measures, if needed;
e Prepare draft and final versions of an MOA that will summarize the Determinations of
Eligibility and Effect, and which will stipulate appropriate measures to mitigate adverse
effects. An initial draft of the MOA will be provided to the City and ACOE for review and
revisions prior to supplying the document to the NHDHR for review. VHB will finalize the
MOA following NHDRR review.
Task 11. Permitting Follow On Services
Following permit application submissions to regulatory agencies, follow-up and coordination
effort is sometimes required to respond to requests for additional information and specific
comments and concerns raised. Work under this task might include:
e Preparation of documents to respond to agency comments;
e Minor plan revisions/additions; or
e Attendance at site inspections by the state or federal agencies,