Professional Engineer, and any other communication about the contract shall be addressed or be
delivered to the City of Nashua Representative.
CHANGES TO SCOPE OF WORK The City of Nashua may, at any time, by written order, make
changes to the general scope, character, or cost of this contract and in the services or work to be
performed, either increasing or decreasing the scope, character, or cost of Professional Engineer's
performance under the contract. Professional Engineer shall provide to the City of Nashua within
10 calendar days, a written proposal for accomplishing the change. The proposal for a change shall
provide enough detail, including personnel hours for each sub-task and cost breakdowns of tasks,
for the City of Nashua to be able to adequately analyze the proposal. The City of Nashua will then
determine in writing if Professional Engineer should proceed with any or all of the proposed
change. If the change causes an increase or a decrease in Professional Engineer's cost or time
required for performance of the contract as a whole, an equitable adjustment shall be made and the
contract accordingly modified in writing. Any claim of Professional Engineer for adjustment under
this clause shall be asserted in writing within 30 days of the date the City of Nashua notified
Professional Engineer of the change.
When Professional Engineer seeks changes, Professional Engineer shall, before any work
commences, estimate their effect on the cost of the contract and on its schedule and notify the City
of Nashua in writing of the estimate. The proposal for a change shall provide enough detail,
including personnel hours for each sub-task and cost breakdowns of tasks, for the City of Nashua
to be able to adequately analyze the proposal. The City of Nashua will then determine in writing
if Professional Engineer should proceed with any or all of the proposed change.
Except as provided in this paragraph, Professional Engineer shall implement no change unless the
City of Nashua in writing approves the change. Unless otherwise agreed to in writing, the
provisions of this contract shall apply to all changes. The City of Nashua may provide verbal
approval of a change when the City of Nashua, in its sole discretion, determines that time is critical
or public health and safety are of concern. Any verbal approval shall be confirmed in writing as
soon as practicable. Any change undertaken without prior City of Nashua approval shall not be
compensated and is, at the City of Nashua's election, sufficient reason for contract termination.
CITY OF NASHUA COOPERATION The City of Nashua agrees that its personnel will cooperate
with Professional Engineer in the performance of its work under this contract and that such
personnel will be available to Professional Engineer for consultation at reasonable times and after
being given sufficient advance notice that will prevent conflict with their other responsibilities.
The City of Nashua also agrees to provide Professional Engineer with access to City of Nashua
records in a reasonable time and manner and to schedule items that require action by the Board of
Public Works and Finance Committee in a timely manner. The City of Nashua and Professional
Engineer also agree to attend all meetings called by the City of Nashua or Professional Engineer to
discuss the work under the Contract, and that Professional Engineer may elect to conduct and record
such meetings and shall later distribute prepared minutes of the meeting to the City of Nashua.
DISCOVERY OF CONFLICTS, ERRORS, OMISSIONS, AMBIGUITIES, OR DISCREPANCIES
Professional Engineer warrants that it has examined all contract documents, has brought all
conflicts, errors, discrepancies, and ambiguities to the attention of the City of Nashua in writing,
and has concluded that the City of Nashua’s resolution of each matter is satisfactory to Professional
Engineer. All future questions Professional Engineer may have concerning interpretation or
clarification of this contract shall be submitted in writing to the City of Nashua within 10 calendar
days of their arising. The writing shall state clearly and in full detail the basis for Professional
Engineer's question or position. The City of Nashua representative shall render a decision within
15 calendar days. The City of Nashua's decision on the matter is final. Any work affected by a
conflict, error, omission, or discrepancy which has been performed by Professional Engineer prior
to having received the City of Nashua’s resolution shall be at Professional Engineer's risk and
expense. At all times, Professional Engineer shall carry on the work under this contract and
GC 3 of 11