Breakdown of Tasks, Personne! Hours, and Cost
BREAKDOWN OF TASKS - WATER STREET FINAL DESIGN
City of Nashua, NH
VHB Water Street Fina Design Fee 2022-05-19 ORAFT
Total
GAIGC & Task Senior $r.CADO =| Admin. / CADD
Tasks PM Managers Engineer Engineer Tech. Tech Hours Labor Amounts
Final Plans (90%)
General Plan
Set Alignment 3 3 $285
Label Curbing Geometry and Provide Curbing Table 2 4 4 10 $1.150
Drainage Modifications and Notes 2 1 4 4 1 $1.365
Consinucton Notes 2 1 3 6 $920
Signing and Pavement Marking Pian 1 4 2 6 10 $1.230
Sign Summary Sheet 4 5 $715
Badge Railing Modifications 2 § 8
Detail Sheet(s) 4 Z 4 4 § 20 $2 880
“Traffic Signal Modifications (Water St at Main Si} 1 2 4 6 13 $4,775
100% Plans Incl, Response to Comments 6 4 2 4 4 4 24 $3,660
Special Provisions 4 4 6 14 $2.590
Coerdination with CM during their Contractor Procurement 4 4 4 12 $2,300
Project Meetings / Cormespondance/Coordination with Cay 12 12 24 $5,160
33 34 18 30 26 24 162 $24,040
TOTAL HOURS 38 4 18 30 26 24 162
HOURLY RATES $216.00 $216.00 $146.00 $96.00 $125.00 $86.00
LABOR COSTS $8,170 $7,310 $2,670 $2,850 $3,260 $2,040 $26,230
TOTAL LABOR = $26 230.00
Date Prepared 6/9/2022