Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Board Of Aldermen - Agenda - 8/9/2022 - P82

Board Of Aldermen - Agenda - 8/9/2022 - P82

By dnadmin on Mon, 11/07/2022 - 07:48
Document Date
Fri, 08/05/2022 - 12:01
Meeting Description
Board Of Aldermen
Document Type
Agenda
Meeting Date
Tue, 08/09/2022 - 00:00
Page Number
82
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/boa_a__080920…

The H.L. Turner Group Inc.

27 Locke Road Concord, NH 03301 = 1: 603.228.1122 hiturner.com

Nashua Riverfront Development Project
Final Engineering Design

5/11/2022
WORK HOURS TOTAL
OESC 1ON
Mosk voli PM Structural PE Sr PO Tc HOURS
Segment 11 - 58-60 Main Street Boardwalk ped Ns
11.1 - Design Bracket Connections 2 16 2 20
11.2 - Transition Design - Boardwalk to Ramp 2 16 2 20
11.3 - Design - Ramp & Piles 2 24 2 28
11.4 - Riverbank Slope E&S 4 16 2 22
115 - Final Drawings & Specifications 8 S6 4 80 8 156
fe Se a SY ce ey ee ee ee es ee ee es ee ee le ee ey ee ee ee ee ee ee ee ee ee es
112 20 | 246
ees ee ee 8 ere se ee ee eee
TOTAL HOURS 18 112 20 80 16 246
ESTIMATED ENGINEERING COSTS
Work Estimated
Hours Hourly Rate Costs
Project Manager (PM} 18 $ 150.00 $ 2,700.00
Structural Engineer (Structural} 112 $ 185,00 $ 20,720.00
Project Engineer (PE} 20 5 130.00 $ 2,600.00
Sr. Project Designer | (Sr PD} 80 5 105.00 $ 8,400.00
Technical Coordinator (TC) 16 § 100.00 $ 1,600.00
246 Total Fully Burdened Labor $ 36,020.00
Subconsultant $ -
Expenses 5 300.00
Estimated Direct Costs $ 300.00

TOTAL ESTIMATED COST: $ 36,320 0D

Page Image
Board Of Aldermen - Agenda - 8/9/2022 - P82

Footer menu

  • Contact