The H.L. Turner Group Inc.
27 Locke Road Concord, NH 03301 =: 603.228.1122 hiturner.com
Nashua Riverfront Development Project
Final Engineering Design
5/11/2022
TASK DESCRIPTION WORKRHOERS reiet
PM Structural PE Sr PD Tc HOURS
Segment 7 - Riverfront Path Along BAE Property
7.1- Erosion & Scour Determination 8 20 2 30
eas | SEWERS ST aie SMS 5 (Si Rad Ree 8 RP AO aes Le 20-0) ie 0 Gass cineca A leet
TOTAL HOURS 8 it) 20 0 2 30
ESTIMATED ENGINEERING COSTS
Work Estimated
Hours Hourly Rate Costs
Project Manager (PM)} 8 S$ 150.00 $ 1,200.00
Structural Engineer (Structural) 0 $ 185.00 $ -
Project Engineer (PE) 20 $ 130.00 S$ 2,600.00
Sr. Project Designer I {Sr PD} fe] $ 105,00 $ -
Technical Coordinator (TC} 2 $ 100.00 $ 200.00
| 30 | Total Fully Burdened Labor $ 4,000.00
Subconsultant $ :
Expenses $ 100.00
Estimated Direct Costs ¢ 100,00
TOTAL ESTIMATED COST: $ 4,100.00