5/11/2022
TASK DESCRIPTION WORK HOURS TOTAL
PM Structural PE Sr PD Te HOURS
Segment 5 - Multi-Use Path Connector
5.1 - Erosion & Scour Determination 8 20 i 30
PUIGITISSII EROS Se SS A
TOTAL HOURS 8 0 20 0 2 30
ESTIMATED ENGINEERING COSTS
Work Estimated
Hours Hourly Rate Costs
Project Manager (PM} 8 $ 150.00 $ 1,200.00
Structural Engineer (Structural) 0 S$ 185.00 5 -
Project Engineer (PE} 20 $ 130.00 $ 2,600.00
Sr. Project Designer | (Sr PD) ie) $ 105.00 $ -
Technical Coordinator (TC) 2 S$ 100.00 S$ 200.00
| 30 | Total Fully Burdened Labor $ 4,000.00
Subconsultant $ -
Expenses § 100.00
Estimated Direct Costs
TOTAL ESTIMATED COST =
$100.00
§ 4,100.00